Restoration Campaigns & Master Planning (2014–Present)
Since 2014, the church has undertaken a series of restoration initiatives guided by a long-term masterplan to maintain the architectural integrity of the landmark and modernize essential building infrastructure. With a total budget of $3 million, these efforts have been phased to support ongoing fundraising and to minimize disruption to the church’s operations and community services.
Key Restoration Milestones:
2016 – North Clerestory Roof Replacement:
Initiated in response to persistent water infiltration and associated interior damage, this first phase addressed critical envelope issues by replacing the flat roof above the north clerestory.
2019 – Comprehensive Exterior Restoration:
This major campaign involved the removal of a non-original asphalt shingle roof and the reinstatement of the historically appropriate slate roofing system. Snow guards were added to protect the original carved gutter stones from future water-related damage.
Additional scope included:
- Dutchman repairs and selective unit replacement at carved stone gutters
- Restoration and partial reconstruction of the building’s original rainwater drainage system
- In-place restoration of the historic stained-glass windows
Notably, this work was completed during the height of the COVID-19 pandemic, requiring emergency work permits, adaptation to supply chain disruptions, and coordination of labor under essential personnel protocols.
Ongoing Work – Accessibility Upgrades:
Currently, the church is undergoing additional site improvements that include the removal of the obsolete bullet-glass sidewalk vault cover and the construction of a new ADA-compliant entrance ramp. The ramp integrates salvaged architectural materials—including a repurposed carved limestone guardrail from the church interior –alongside new bronze handrails and limestone steps that tie seamlessly into the existing elevation of the main entrance.

Aerial image of site

View of roof as seen from the New York Historical Society

Nave and chancel archive photo ca 1899 - Library of Congress

Entrance archive photo ca 1899 - Library of Congress

View of gable wall stone cross

View of stone 

Original dutchman stone repair in excellent condition

View of the pinnacled four-section tower

Architectural general arrangement elevation drawing excerpt

Architectural general arrangement elevation drawing excerpt

Architectural detail drawing excerpt

Architectural detail drawing excerpt

View of completed restoration campaign as seen from the New York Historical Society

Detail view of restored slate roof along W 76th Street

Detail view of restored slate roof above the clerestory wall

View of completed restoration campaign along Central Park West looking north

View of Central Park West elevation looking west

View of Central Park West elevation looking south

Detail view of restored slate roof at nave

Detail view of restored slate roof at transept

Detail view of restored slate roof and rainwater goods at nave

Detail view of restored profiled limestone gutter stones at transept